Connect with us

News

MARTA Board Approves Expansion Timeline

    More MARTA Atlanta Program Paves the Way for Increased Connectivity and Economic Development

The Metropolitan Atlanta Rapid Transit Authority Board of Directors has unanimously approved the sequencing of the transit projects in the More MARTA Atlanta program.

This partnership between MARTA and the City of Atlanta kicks off the largest investment in public transit since MARTA’s inception 40 years ago, including almost $1.3 billion for direct connectivity to and around the Atlanta BeltLine. The program of projects introduces new modes to the MARTA system, with 14 new miles of bus rapid transit (BRT) representing 22% of the expansion miles; 22 miles of arterial rapid transit (ART) representing 34% of the expansion; and 29 new miles of light rail service representing 44% of the new service. With these new modes and a significant expansion of light rail, MARTA is building a balanced, smart transit system to serve current customers and attract new riders in Atlanta and across the region.

This expansion program marks a major shift in MARTA’s approach to project delivery, with a commitment to seeking public-private partnerships that will generate new sources of revenue and allow for faster completion of projects. The partnership with the Atlanta BeltLine is central to the expansion program and is reflected in the early sequencing of projects that provide BeltLine connectivity in the southeast (Summerhill BRT), to the southwest (Campbellton Road LRT) and the Eastside Trail (Streetcar East Extension and North Avenue Phase 1 BRT). MARTA’s collaboration with Emory University will transform our ability to connect people to the more than 40,000 jobs along the Clifton Corridor and improve access for over 2 million patients who visit Emory University Hospital and the Atlanta Veterans Affairs Medical Center each year.

“This program is a game changer,” said MARTA General Manager and CEO Jeffrey Parker. “We will have more and better transit options to get to job centers, colleges and universities, hospitals, parks and neighborhoods across Atlanta. With our focus now on the projects instead of the types of transit, we are ready to begin implementing the plan for enhanced service.”

“The More MARTA Atlanta program will help reach some of our most vulnerable residents, providing them access to opportunity and jobs, while enhancing our public transportation system in a way that will have a positive impact on both economic development and quality of life,” said Atlanta Mayor Keisha Lance Bottoms.

“The Atlanta BeltLine was always envisioned as a transportation corridor, a plan validated by Atlanta voters in 2016,” said Clyde Higgs, President and CEO of Atlanta BeltLine, Inc. “The adoption of the More MARTA phasing today is a start towards fulfilling the promise of transportation options to some of the largest hubs for economic and workforce development along the BeltLine.” ABI is the City of Atlanta’s implementation agent for the Streetcar System Plan.

The board approval sets in motion a four-decade expansion program that will continue to evolve to best meet the needs of the community and leverage opportunities in new technologies, innovative partnerships, real estate and transit-oriented development as they present themselves, that can provide increased mobility, accessibility and reliability for transit users.

In determining the sequence of the projects, MARTA considered market conditions, constructability and current funding commitments. Recognizing changes in those key areas are possible, the following proposed schedule is currently in effect:

Operational by 2025:

  • Capitol Avenue (Summerhill) BRT: a bus rapid transit line linking commercial, government and education centers and the Atlanta BeltLine’s Southside Trail
  • ART projects:
  • North Avenue BRT Phase I: connecting the BeltLine’s Eastside Trail and Poncey-Highland to North Avenue Station
  • Bankhead Station improvements: lengthening the platform to accommodate eight-car trains and significant growth in the neighborhoods surrounding the station

Under construction by 2025:

  • Streetcar East Extension: an approximately two-mile route along the Atlanta BeltLine connecting the existing Atlanta Streetcar to Ponce de Leon Avenue through popular intown neighborhoods Inman Park, Old Fourth Ward and Poncey-Highland
  • Greenbriar Transit Center: a multi-modal transit hub connecting local bus service to high-capacity transit on Campbellton Road
  • Five Points Station improvements

Planning and design phase by 2025:

  • Campbellton Road high-capacity transit: approximately 5 miles of service from Oakland City Station to the Greenbriar Transit Center
  • Clifton Corridor Phase 1: light rail linking Lindbergh Center Station to Emory University, Emory Hospital, the Centers for Disease Control, Children’s Healthcare, and Veteran’s Administration Hospital
  • Southwest BeltLine: approximately 3.5 miles of light rail service from Oakland City Station to Westview Drive near I-20, where it would connect to the future western extension of the Atlanta Streetcar
  • Northeast BeltLine: approximately 3.5 miles of light rail service between Ponce City Market and Lindbergh Center Station/Armour Yard area

Newsletter Signup

Join our email list to stay connected.

Written By

5 Comments

5 Comments

  1. Pingback: Best universities in Africa

  2. Pingback: about us

  3. Pingback: จำหน่าย Access Control

  4. Pingback: https://www.tinnitustalk.com/proxy.php?link=https://gasdank.com/

  5. Pingback: auri mushroom gummies

You must be logged in to post a comment Login

Leave a Reply

Advertisement
Advertisement

Advertisement

Newsletter Signup

Join our email list to stay connected.

©2019 Atlanta Tribune: The Magazine

Connect
Newsletter Signup

Join our email list to stay connected.

Verified by MonsterInsights